Hey there.

I am working on projects where one task commences immediately as another finishes.

For example,

take cake out of oven - Cook 1 (Resource)
time for cake to cool - No resource

Obviously the cake starts cooling as soon as the previous task starts.

How can I fix the start time of taking the cake out of the oven to the start of the cooling time?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Need to set task to start before another task completes Hugmongous OmniPlan General 1 2012-09-26 01:29 PM
Start a task as late as possible? cvandyck OmniPlan General 10 2012-09-15 12:33 AM
What is a aunt task / Relationship & assigning dependencies with parent/child tasks qubit OmniPlan General 2 2012-09-04 12:16 PM
2 dependencies in the same task Kimsake OmniPlan General 2 2008-05-16 12:08 PM
locking the start of a task immediately upon completion of the previous task mr_projects OmniPlan General 0 2007-10-30 08:12 AM