Hi,
I have a question regarding the leveling priorities.
In the Omniplan manual I found :
In judging which task to put first, the following criteria matter, in this order:
Requirements to end by a certain time, such as locked end dates, con- straints, or being a prerequisite to a task with such a requirement.
Task Priority, as set in the Priority column of the task outline.
Position in the task outline; tasks with lower ID numbers are scheduled earlier.
I really cannot see the use of the third priority, the ID number.
I got a reply from the Omniplan people that some users wanted to see a waterfall scheduling and that was the reason the ID number priority was implemented.
However this stands in the way of an optimized scheduling. In screenshot 1, one can see the scheduling after leveling and after task BC has been moved from ID number 1 to ID number 16, the scheduling is ok like this.
When one schedules again however, now because task BC has ID-number 16 you get a warning, the scheduling is not ok anymore. (screenshot 2)
This is easy to solve when you only have 16 tasks but if it were 80 it is harder to find out what went wrong. I can understand that one can gives a higher priority to a task in the priority field but would like to ask to cancel the ID-number as far as the leveling priority is concerned,
Best regards,
I have a question regarding the leveling priorities.
In the Omniplan manual I found :
In judging which task to put first, the following criteria matter, in this order:
Requirements to end by a certain time, such as locked end dates, con- straints, or being a prerequisite to a task with such a requirement.
Task Priority, as set in the Priority column of the task outline.
Position in the task outline; tasks with lower ID numbers are scheduled earlier.
I really cannot see the use of the third priority, the ID number.
I got a reply from the Omniplan people that some users wanted to see a waterfall scheduling and that was the reason the ID number priority was implemented.
However this stands in the way of an optimized scheduling. In screenshot 1, one can see the scheduling after leveling and after task BC has been moved from ID number 1 to ID number 16, the scheduling is ok like this.
When one schedules again however, now because task BC has ID-number 16 you get a warning, the scheduling is not ok anymore. (screenshot 2)
This is easy to solve when you only have 16 tasks but if it were 80 it is harder to find out what went wrong. I can understand that one can gives a higher priority to a task in the priority field but would like to ask to cancel the ID-number as far as the leveling priority is concerned,
Best regards,
Last edited by luke18; 2011-09-20 at 01:03 PM.. Reason: Attachments not there