I'm using OmniPlan 1.1.2 and have a project's default calendar to use a work week of 7 days (instead of the usual M-F 5 days). However, when I assign effort of 5 days to a task, it becomes 1w instead of staying at 5d. Similarly, a task that is planned for a calendar week (say, Thursday to Thursday) shows up as consuming more than a week.

I'd appreciate any advice how to reconcile the schedule with the effort data.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
What I did last week adrianwi OmniFocus 1 for Mac 3 2010-06-14 08:29 AM
First day of the week? FlyingBarney OmniFocus 1 for Mac 2 2009-05-16 01:52 AM
Due within Next Week? gumby911 OmniFocus 1 for Mac 1 2008-05-07 11:00 PM
Due Next Week...or Whenever julrdrgz OmniFocus 1 for Mac 3 2008-01-18 08:51 PM


All times are GMT -8. The time now is 05:11 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.