I'm fairly new to OmniPlan, but very familiar with project planning. I've entered my tasks and resources into OmniPlan and now I want to show how much effort I've assigned to a resource. I've checked the online help and this forum, but I don't see any suggestions on how to get this calculation. Any suggestions? I also checked for a general reports menu item to spit out various reports and there doesn't seem to be any.

Thanks,
Mike King
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource effort per task andrey44 OmniPlan General 0 2012-11-26 07:21 AM
Sum up effort for a resource trinix OmniPlan General 2 2012-01-30 10:39 AM
Tutorial - resource/effort/duration confusion billobermeyer OmniPlan General 1 2009-07-28 01:39 PM
Splitting effort for a single resource bugmenot OmniPlan General 2 2007-03-07 05:01 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM