I normally sort by Name, but even if I have it set up as you do, it still doesn't work.
My projects have no start or due dates, but they all have review dates set to every 1 day.
I was a few days behind this morning, so I Mark Reviewed everything in the past and in the Yesterday group. Those items disappeared correctly.
But when I started doing Mark Reviewed on Projects in the Today group, I noticed nothing was disappearing. The Inspector updated the Project's Review status as being "Last: Oct 8, 2007 4:38 PM" but the Project did not disappear from the Today group. Nor did the "next review" date/time increment up correctly to tomorrow for any of them.
This all used to work. The reason I feel so sure about this is because I had a Perspective set up for this process and used it a couple days in a row as I recall.
But maybe the problem is that I got behind. Maybe this workflow that I was using gets screwed up if I get a day off. Dunno.
As a test, I have now selected all active Projects (in a different view), marked all of their Review dates for tomorrow 12:00 a.m., and they correctly ONLY show up in the Tomorrow group in my Review Perspective. So now my Review Perspective has nothing in it for Today.
I'll wait for tomorrow to come, see what then appears in the Today group, and test to see if Mark Reviewed works on those items then.
If it does, it's just a matter of reviewing EVERYthing EVERYday--or the program gets confused and doesn't function correctly anymore.
Unless it's some other bug affecting the Mark Reviewed feature.
Sandy
Quote:
Originally Posted by Chris
I take it you're in planning mode, grouping by "Next Review" and sorting by "Next Review"? I'm doing that now with the latest build, and when I click "Mark Reviewed", the projects disappear from the current group ("Within the last month" for me) and reappear in the right place.
What I do notice is that if I group by folder but sort by "Next Review", the folder at the top isn't the one with the oldest review date.
|