can I assign a default due date for a project. I want a particular due date for any action I create in a particular project.
 
Well sort of. If you give a project a due date, actions within it will behave as if they have that date without actually showing their own due date, yet you can still give them earlier dates if you want to.

In fact you can also give them later dates, but they'll still behave as if they were due on the project due date. I'm not sure that's right - I can see situations where you'd want to complete a project on a given date, yet still have follow up actions due after the main completion, such as "obtain user feedback".

Mark
 
thanks. That works for me.
 
Quote:
Originally Posted by MacBerry View Post
In fact you can also give them later dates, but they'll still behave as if they were due on the project due date. I'm not sure that's right - I can see situations where you'd want to complete a project on a given date, yet still have follow up actions due after the main completion, such as "obtain user feedback".
That's the case for me, from time to time. I deal with it during my (usually) weekly review, by assessing whether the project is done, except for followup, and then adjusting the due date if it is.
 
Another way to deal with "post mortem" items is to make the by-project-deadline items into an action group. For example:

Code:
- Attended conference  (set to sequential, no due date)
  - Prepared for conference (due by date of conference)
    - Tasks to get ready for conference...
    - ...
  - Submitted expenses for conference (start date after conference)
  - From employer, reimbursement for conference
All the tasks to get ready for the conference in my example will inherit the due date of their parent, but the expense related tasks won't have a due date. Prepared for conference could be a sequential or a parallel action group depending on the nature of the tasks inside it.

Nesting action groups and changing their parallel/sequential status is a powerful way to express dependencies between tasks.
__________________
Cheers,

Curt
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Making Start Date, Due Date, Estimate Default jessicatmt OmniFocus 1 for Mac 1 2012-08-06 01:23 PM
default due date and project burgessa23 OmniFocus 1 for Mac 10 2009-08-04 04:57 PM
Date columns in default context view; default views in general noumenal OmniFocus 1 for Mac 2 2009-02-02 08:20 AM
Default project, default context? BevvyB OmniFocus 1 for Mac 2 2008-09-04 10:51 AM
set default context, project, date, time for actions deejaydoc OmniFocus for iPhone 0 2008-08-13 05:45 PM


All times are GMT -8. The time now is 07:17 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.