2 resources on the same task Thread Tools Search this Thread Display Modes
While it sometime works, I often seen the following happen:

Take one task (let's say 1 week worth of work) and assign one resource to it, then another. Sometime it'll reduce it to 2.5 days (good) but sometime the tasks time will grow infinite (or seemingly so) and you can't really fix it unless you remove a resource.

Anyone seen that ? It's not reproducable all the time.

Erik
 
Yup. We think we've got this one sorted out -- give a shout if it still happens in the next beta.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
One task, two resources, different hours Bridgeblox OmniPlan General 8 2013-03-15 02:57 PM
same task/different resources (courses/classes) loic OmniPlan General 0 2011-09-05 03:54 AM
One task, three resources, how do I get an accurate total cost? jimantonopoulos OmniPlan General 1 2011-04-18 10:49 AM
Task Costs With Multiple Assigned Resources dmabram OmniPlan General 1 2008-03-13 12:48 AM


All times are GMT -8. The time now is 11:43 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.