Help with Resources, Using crews of people Thread Tools Search this Thread Display Modes
Here is what I am trying to do.
I have a foreman "Austin F." he spends 50% of his time on foreman responsibilities. The other 50% is divided between crew 1 and 2. What do I need to enter in the Units and Efficiency boxes to make this all work out.

I am also hoping that I can assign all the members of a crew by selecting the group they are in. Some of my crews are 15 people or better and selecting each one would take forever on a large job. Currently when I select the group the dialog says 1 of 2.

Just to wrap it all up.
I want to be able to select a task, click on the crew I want to accomplish that task, and have each member of that crew assigned to the task including the foreman for that crew at x%

Thanks in advance.
I have been going around in circles to the point I have muddied the water and can't see my way out.
Attached Thumbnails
Click image for larger version

Name:	OmniP1.jpg
Views:	196
Size:	67.8 KB
ID:	1214  
 
Quote:
Originally Posted by twobarb View Post
Here is what I am trying to do.
I have a foreman "Austin F." he spends 50% of his time on foreman responsibilities. The other 50% is divided between crew 1 and 2. What do I need to enter in the Units and Efficiency boxes to make this all work out.
You could create Austin F. as a resource with 100% units and when Austin is assigned to a foreman task you'll need to go to the Task : Assignment inspector and change the percentage to 50% of 100%. If Austin is assigned to a Crew 1 or 2 task, do the same thing but change Austin to 25% instead.

Quote:
Originally Posted by twobarb View Post
I am also hoping that I can assign all the members of a crew by selecting the group they are in. Some of my crews are 15 people or better and selecting each one would take forever on a large job. Currently when I select the group the dialog says 1 of 2.
The group resource doesn't work this way currently. If you assign a group resource to a task it doesn't assign every resource to the task, it's supposed to automatically pick one available resource within a group for the task after you level the project. In other words, I need someone from my electrical team to look at this task ASAP but I don't care who, just let OmniPlan find the first resource from the electrical team and assign him/her to it.

Quote:
Originally Posted by twobarb View Post
Just to wrap it all up.
I want to be able to select a task, click on the crew I want to accomplish that task, and have each member of that crew assigned to the task including the foreman for that crew at x%
There isn't a way to do this now but I'll file a feature request for this in our database for consideration.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How do people use Folders? klaing OmniFocus 1 for Mac 4 2010-10-29 06:42 AM


All times are GMT -8. The time now is 06:14 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2020, vBulletin Solutions, Inc.