13 months in a year?? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I am trying to set up a plan with units of months over a four year period. When I create a task and give it a duration of 48 mo starting at 'T', it is shown on the Gantt chart as lasting for about 3 years and 9 months, and in the task inspector as having a duration of 191w and 4d. If I manually stretch the task bar until it reaches the 4 year mark, it is shown as having a duration of 52 months!

I guess that I need to do something with the calendar or with the effort conversion factors, but what? Since I am only planning in months, I don't care about the time or length of the working week, or anything like that.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Hide Due within 3 and 6 months? and others? amityweb OmniFocus 1 for Mac 6 2012-11-06 11:30 AM
Changing date from month/day/year to day/month/year RickM OmniPlan General 2 2009-01-27 09:06 AM
My months with OmniFocus sriggins OmniFocus 1 for Mac 7 2008-06-19 08:42 PM
working in months only? jshahin OmniPlan General 1 2007-04-22 10:28 PM
3 months behind sriggins OmniWeb General 1 2006-07-03 04:39 PM


All times are GMT -8. The time now is 10:34 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.