Here's my example:

TASK LIST

1) "Post ad to Craigslist - day 0" (15m) (Resource - ME)
2) "Let ad run" (Unassigned)
3) "Check email for replies to ad and repost if necessary - day 1" (15m) (Resource - ME)
4) "Let ad run" (Unassigned)
5) "Check email for replies to ad and repost if necessary - day 2" (15m) (Resource - ME)

When I level it, I WANT this all to adjust based on MY availability, with the "Let ad run" task adjusting effort accordingly.

What is the best way to achieve that?

Thank you in advance for your input!

Nathan
 
Two approaches:

1) Make the durations of tasks 2 and 4 the minimum time you want your ads running. And assign the resources as you have described. Set Finish->Start dependencies between each step in your chain. OmniPlan won't make tasks 2 and 4 the maximum length, but it will delay tasks 3 and 5 until you're available.

2) Don't make 2 and 4 tasks at all. Instead, set a lead time on the dependencies from 1->3 and 3->5. Those lead times should be whatever minimum time you want your ads running. Assign the remaining 3 tasks to yourself. As in option 1, OmniPlan will delay tasks 3 and 5 until you're available to do them.

As long as tasks 2 and 4 aren't costing you money or using equipment resources that other tasks might want to share, either of these should be a decent approximation. But they don't work if, for example, Craigslist charges you for however long your ads run, and you need to accurately track that in your Plan.
 
Quote:
Originally Posted by Lizard View Post
Two approaches:

1) Make the durations of tasks 2 and 4 the minimum time you want your ads running. And assign the resources as you have described. Set Finish->Start dependencies between each step in your chain. OmniPlan won't make tasks 2 and 4 the maximum length, but it will delay tasks 3 and 5 until you're available.

2) Don't make 2 and 4 tasks at all. Instead, set a lead time on the dependencies from 1->3 and 3->5. Those lead times should be whatever minimum time you want your ads running. Assign the remaining 3 tasks to yourself. As in option 1, OmniPlan will delay tasks 3 and 5 until you're available to do them.

As long as tasks 2 and 4 aren't costing you money or using equipment resources that other tasks might want to share, either of these should be a decent approximation. But they don't work if, for example, Craigslist charges you for however long your ads run, and you need to accurately track that in your Plan.
Thanks you for the post.
_________________
Watch Vampires Suck Online Free
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
"floating" time support (11am no matter what time zone) nealxu OmniFocus 1 for Mac 1 2011-06-06 03:11 PM
How to create task with "due date" BUT without "due time" ? fire00 OmniFocus 1 for Mac 3 2010-04-13 11:36 PM
One more time "Waiting For" / "On Hold" offline81 Applying OmniFocus 9 2010-03-29 10:42 AM


All times are GMT -8. The time now is 09:52 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.