I had a project planned in OP. After a while, more or less 1 week, I went back to mark some tasks as completed, and to make some changes in the others. Then I used the button to level the load, and OP moved my future tasks to past dates, taking the place of the completed tasks! In other words, it's like OP does not know the current date, or thinks we can go back in time to perform new tasks!
Has someone else noticed this? How am I supposed to keep track of a project and adapt it along the way?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Getting images to load wman OmniWeb General 1 2009-04-10 08:57 AM
CPU Load = 13% ? lwhitten OmniFocus 1 for Mac 1 2008-03-28 01:56 PM
% complete not working at group level pslade OmniPlan General 9 2007-03-05 11:33 AM
Load All Images Drayon OmniWeb General 0 2007-02-03 10:02 PM
OW won't load a page m-rick OmniWeb Bug Reports 14 2006-11-26 02:21 PM


All times are GMT -8. The time now is 04:42 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.