The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan for iPad
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Task Dependencies - Must start at commencement of another task Thread Tools Search this Thread Display Modes
Hey there.

I am working on projects where one task commences immediately as another finishes.

For example,

take cake out of oven - Cook 1 (Resource)
time for cake to cool - No resource

Obviously the cake starts cooling as soon as the previous task starts.

How can I fix the start time of taking the cake out of the oven to the start of the cooling time?
 
What probably makes the most sense here is to use a lead time for the cooling period. Make a finish-start dependency from the "take cake out of oven" task to the task where you remove it from its pan or decorate it or whatever, and assign the necessary delay by editing the dependency in the editor. Select the task, bring up the editor, tap on Sdheduling, tap on the > in blue next to the dependent, edit the lead time.
 
Quote:
Originally Posted by whpalmer4 View Post
What probably makes the most sense here is to use a lead time for the cooling period. Make a finish-start dependency from the "take cake out of oven" task to the task where you remove it from its pan or decorate it or whatever, and assign the necessary delay by editing the dependency in the editor. Select the task, bring up the editor, tap on Sdheduling, tap on the > in blue next to the dependent, edit the lead time.
Thanks. Project Management newbie.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Need to set task to start before another task completes Hugmongous OmniPlan General 1 2012-09-26 02:29 PM
Start a task as late as possible? cvandyck OmniPlan General 10 2012-09-15 01:33 AM
What is a aunt task / Relationship & assigning dependencies with parent/child tasks qubit OmniPlan General 2 2012-09-04 01:16 PM
2 dependencies in the same task Kimsake OmniPlan General 2 2008-05-16 01:08 PM
locking the start of a task immediately upon completion of the previous task mr_projects OmniPlan General 0 2007-10-30 09:12 AM


All times are GMT -8. The time now is 11:41 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.