Task turned Hammock; its effort reduced Thread Tools Search this Thread Display Modes
I'm trying to create a hammock task. In attempting to recreate the tutorial (glue; let glue dry; spray top coat), I've set a "let glue dry" effort of 3H. After creating the dependencies the way I *think* they're supposed to be, and then turning the "let glue dry" task into a hammock, it's duration is reduced to .25H (or whatever effort I set the "spray top coat" task to. In the attached .png, I have no resource attached to the hammock task, but even when I assigned it to a resource "factory", the results are the same. Perhaps my dependencies are wrong.

The attached PNG is how things look just prior to to changing the task 2 to a hammock task.
Attached Thumbnails
Click image for larger version

Name:	Pre_hammock.png
Views:	657
Size:	39.0 KB
ID:	2492  

Last edited by omnibob; 2012-08-14 at 07:59 AM..
 
Omni explained to me that I just need to set the start date/time of task 3 to wherever is needed, to adjust the length of the hammock. Problem solved.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
How to use hammock task for client feedback? jefvdv OmniPlan General 1 2013-04-11 02:46 PM
Resource effort per task andrey44 OmniPlan General 0 2012-11-26 07:21 AM
Zero effort task charlax OmniPlan General 2 2012-03-02 04:01 PM


All times are GMT -8. The time now is 03:11 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.