This may be an entirely stupid question; I am not the most experienced project software user... but...
When I want to do some manual levelling, I find it frustrating that I am not able to do it directly in Resource view. Switching back to the Task view and finding the task amongst a lot of others is time consuming. (Some would say boring!)
What I would like to do is quickly slide around the tasks (start/end) in Resource view, without having to switch back to Task view. I don't think this is possible at the moment.
Failing that, some sort of filtering in Task view; so that I can filter the displayed tasks by Resource, Date, Duration, etc., would be great...
When I want to do some manual levelling, I find it frustrating that I am not able to do it directly in Resource view. Switching back to the Task view and finding the task amongst a lot of others is time consuming. (Some would say boring!)
What I would like to do is quickly slide around the tasks (start/end) in Resource view, without having to switch back to Task view. I don't think this is possible at the moment.
Failing that, some sort of filtering in Task view; so that I can filter the displayed tasks by Resource, Date, Duration, etc., would be great...