I have several groups of tasks. Each group has couple of dozen tasks. I am not allowed to start tasks from Group 2 until *every* the tasks from Group 1 is not started. Cannot start any task from group 3 until every task from Group 2 is not started. and so on. How do I do that?

I cannot use simple group dependency since Omniplan allows start of any task from Group 2 if any task from Group 1 has started.

Please help.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
How to set dependencies on the iPad chuckbo OmniFocus for iPad 2 2010-09-01 12:09 PM
OUIEditableFrame dependencies tommetge Omni Frameworks 2 2010-08-06 07:28 AM
Clarity of dependencies sunshine OmniPlan General 3 2008-11-04 05:52 PM
2 dependencies in the same task Kimsake OmniPlan General 2 2008-05-16 12:08 PM


All times are GMT -8. The time now is 05:55 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.