Calendar Exceptions - how to use? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi,

I've created a task, assigned to resource 'X'. In resource 'X's profile I've entered an exception in their calendar for two weeks since they're on vacation. This exception time happens during the created task.

I would have expected this to cause the task to extend by two weeks and mark the vacation period on the plan - but instead, it just marks the task as having a violation due to the exception.

Am I doing this wrong? I just want to be able to factor vacation times into my plans and this does seem to be the right approach but it just doesn't do what I would expect...

Thanks,

Jamie.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
A lot of exceptions being thrown in my logs krunk OmniFocus 1 for Mac 1 2010-02-27 04:02 PM
Remove Schedule Exceptions lsamberg OmniPlan General 3 2009-10-30 02:57 AM
Assertion exceptions tslarkin Omni Frameworks 1 2009-03-23 08:18 AM
Exceptions and Overtime??? hoju OmniPlan General 1 2008-01-24 11:30 AM


All times are GMT -8. The time now is 07:32 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.