Hello,

I am a new registered user of OmniOutliner.

Is there a way for the parent to reflect in percent how many of the children tasks are completed? For example:

33% [ ] Parent Task
[ ] Child task 1
[x] Child task 2
[ ] Child task 3

I know I can use the numbers column but then every time I add a new task I would have to figure by hand what the new percentage is for that task.

All tasks are weighted equal.

Thank you!

Last edited by New Horizon; 2009-12-24 at 01:23 AM..
 
I figured it out:

I Created a column and called it "% Completed." I defined the column type to be "Number," the Summary to be "Average Leaves," and the Format to be "10000%."

As I work the project, I assign what the percent completion is for each task. All the tasks get rolled up to the parent for the total percent completed.

Last edited by New Horizon; 2009-12-24 at 07:33 AM..
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Mark project as completed (automatically) jordyvt OmniFocus 2 for Mac (Private Test) 2 2013-04-01 10:36 AM
Popup to ask if project is completed when last action completed esciara OmniFocus 1 for Mac 2 2007-09-04 03:59 AM
Marking a completed project as "completed" jenniferp OmniFocus 1 for Mac 3 2007-07-03 12:30 PM
'Completed' project - GUI vs. Applescript RobTrew OmniFocus 1 for Mac 1 2007-06-25 08:38 PM


All times are GMT -8. The time now is 05:08 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.