I have a bunch of tasks that I want to start as soon as possible, then they all need to wait until after a dependency finishes, then they have another 3 days of effort left.

Any ideas how to plan for this up front? I know how to split tasks, but how do I get the first part to start ASAP (no dependencies) and the second part to start after the dependency finishes and take 3 more days?

One of the reasons I don't want to show it as two separate tasks linked with a dependency is that I want to assign the resource from a pool of 4 developers and I want the program to auto level. Of course the same developer needs to work on both parts of the task.

Thanks,
Mike
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Split task or group? amarkelo OmniPlan General 2 2013-04-01 05:08 PM
How to ensure a task is not split between days? hmtucaz OmniPlan General 2 2012-06-19 04:37 PM
What is a Split Task joelande OmniPlan General 0 2012-03-16 01:53 PM
How do you unsplit a split task? yahoo160 OmniPlan General 3 2012-02-10 02:50 PM
Split a task in some hours per day lollo17 OmniPlan General 0 2011-04-22 08:01 AM


All times are GMT -8. The time now is 01:03 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.