The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Reporting by month Thread Tools Search this Thread Display Modes
Is there a way within OmniPlan to generate reports, either from within the program or programmatically? The data I am after in particular is the amount of hours a particular resource is scheduled for by month going forward.

Any ideas about how to about getting to this?
 
To follow-up on this, I am after the monthly scheduled hours per resource to inform hiring and staffing decisions. I've planned out all of our tasks, assigned them to resources, leveled, etc. In the resource view I can see where the pain points are in terms of resource load (red bars), but I am not exactly clear as to what over 100% of the resource load means. Does over 100% mean 5 hours over for that week or are 100 hours scheduled for that particular resource? I have no idea how to find this out.

Any ideas?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
iCal reporting iangall OmniPlan General 0 2009-09-18 04:59 PM
Changing date from month/day/year to day/month/year RickM OmniPlan General 2 2009-01-27 10:06 AM
Reporting?? signal15 OmniFocus 1 for Mac 5 2008-09-26 01:14 PM
Due Soon not reporting Smhearty OmniFocus for iPhone 2 2008-07-21 02:26 AM
Reporting... loungeapple OmniPlan General 1 2007-03-05 02:03 PM


All times are GMT -8. The time now is 10:16 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.