Splitting effort for a single resource Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I'm trying to create a plan that involves people dedicating a percentage of their time each week to a couple of different tasks that run in parallel. The start/finish dates are not identical for the two tasks so one will finish before the other. Now, how can I get these resources to dedicate 100% of their time on the remaining task instead of the allocated percentage that's required when both are running?

It's nice that OP tells me when a resource is over/under utilised but why I can't I maximise resource usage across several things??
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource effort per task andrey44 OmniPlan General 0 2012-11-26 07:21 AM
Reporting on Resource effort Elessar OmniPlan General 0 2012-06-20 08:33 AM
Sum up effort for a resource trinix OmniPlan General 2 2012-01-30 10:39 AM
Tutorial - resource/effort/duration confusion billobermeyer OmniPlan General 1 2009-07-28 01:39 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM


All times are GMT -8. The time now is 06:15 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.