Hello,

I am using OP 2.01. I have a project (opening a hotel) in the future. Iam working backwards from that date.
I want to use the duration of each single task not based on a work week but on normal 24 hours days. Let's say today in 7 days I have to order something. So I need OP to let me enter 7 days which is for me exactly one week. Whenever I try this, the start and end date in the Chart doesn't reflect this correctly. I tired already everything and it drives me nuts.

Any ideas.

Thanks a lot.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing working hours in forecast view xkaly OmniFocus for iPad 2 2012-04-08 02:34 PM
Working Hours For A Day In Applescript bjmclaughlin OmniPlan Extras 4 2011-04-06 02:37 AM
can not enter lengths for connected lines oliver_omni OmniGraffle General 3 2009-11-28 10:50 AM
problem about orthogonal connected line routine_work OmniGraffle General 2 2009-01-27 02:00 AM
Effort not connected to duration bbruck OmniPlan General 1 2008-11-04 05:43 PM


All times are GMT -8. The time now is 06:56 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.