Hi, I have a problem with the project cost and it would be great if someone could help with my headache!
I have added the resource costs for each task separately under Inspectors >Task information. Note: not all of my tasks in the project bear cost.
When I highlight the entire project in the outline view and then go: Inspectors>Task information: cost, the total value of the project is 28k but when I export the same plan into HTML and upload it onto the server, the cost of the project displays as 65k.
I have been through all project's tasks separately and manually checked that in Inspects>Task: information, only the tasks that do bear costs have cost assigned to them.
Still, the total value of the project varies when looking at online and offline version.
Is there anywhere else that I should be checking the total project cost?
Many thanks for any suggestions
K.
I have added the resource costs for each task separately under Inspectors >Task information. Note: not all of my tasks in the project bear cost.
When I highlight the entire project in the outline view and then go: Inspectors>Task information: cost, the total value of the project is 28k but when I export the same plan into HTML and upload it onto the server, the cost of the project displays as 65k.
I have been through all project's tasks separately and manually checked that in Inspects>Task: information, only the tasks that do bear costs have cost assigned to them.
Still, the total value of the project varies when looking at online and offline version.
Is there anywhere else that I should be checking the total project cost?
Many thanks for any suggestions
K.