I am the only staff resource on my project. As a result, I have a number of tasks which I will complete concurrently.

1) If I am doing two things at once how do I put this into effort, duration etc.

2) Amongst all my tasks, I have several tasks which will take one day per month over a period of six months. e.g. they are monthly tasks. I have set it up for the start date to be the start of month one and the end date to be the last date in month six. I have no idea how to set things up so that I show that I am only working 6 days in total on this.
 
To divide your energy among a couple of concurrent tasks, you use the task inspector to set the assigned amount of the resource for each task. For example:

Note that I put in 1h effort for Task 1, but it takes 2h duration because I'm only spending half of my time on it. I don't know how to get it to allow me to work full-throttle on Task 2 once Task 1 finishes without splitting Task 2 into 2 pieces.

For your other question, the answer is that you can't do that (yet) -- no support for segmented tasks. You have to put each one of those one-day tasks in separately.

Last edited by whpalmer4; 2008-09-18 at 03:26 PM..
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Tracking Resources Used archeus OmniPlan General 3 2011-05-09 01:35 PM
Time Between Resources scottb OmniPlan General 1 2011-03-31 12:19 PM
non-substitutable resources? tburton OmniPlan General 5 2008-10-01 11:58 AM
Allocating Resource to Task by Hours nitrobin OmniPlan General 0 2008-02-15 09:10 AM
Allocating Variable Funds to Resources havocpub OmniPlan General 1 2006-08-03 09:20 PM


All times are GMT -8. The time now is 10:21 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.