Hi-
I just tried assigning two resources each to a task at 50% each, and it made the task (apparently) infinite in duration. Switching one of them to 25% made it return to its proper size. Removing one of the resources also normalized again.
Adam
I just tried assigning two resources each to a task at 50% each, and it made the task (apparently) infinite in duration. Switching one of them to 25% made it return to its proper size. Removing one of the resources also normalized again.
Adam