Separating task effort from duration Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Perhaps I do not understand the distinction between effort and duration.

I have a task that lasts, say, 1 hour, but the assignee can take up to a week to complete the task.

1) Is this the correct way to distinguish effort (the 1 hour) from duration (the week)?

2) In OmniPlan for iPad, can effort and duration be disconnected? (They are locked to equal values now.). How can you disconnect them?

Many thanks!
Doc
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Different units for duration and effort? LJRolf OmniPlan General 3 2011-02-07 10:39 AM
Effort vs. duration vs. period of a task vs. workload Woje OmniPlan General 2 2008-03-20 08:38 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 05:08 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.