Task due in 5 weeks is "Due Tomorrow" Thread Tools Search this Thread Display Modes
I am just getting started with OmniFocus. I have entered a bunch of projects and tasks. When I click the Due icon, I see 3 sections: Due Yesterday, Due Today, and Due Tomorrow. Everything looks OK, except there is one task in Due Tomorrow that has a start date of February 23, with a due date of February 27. Today is January 20. I've triple checked the dates and cannot figure out why that is showing up now. Any suggestions?
 
An action in a project or action group with a more restrictive due date is treated as though it has the more restrictive due date. You probably have a due date on the project.
 
Yes, that was it. I didn't realize I had put dates on the project. Thanks for your help.
 
It's usually a good safety net, that behavior. Otherwise, you think "oh, I can just defer this another day" over and over, not realizing the whole project had a due date :-)
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing the time "tomorrow" begins mgorman85 OmniFocus 1 for Mac 4 2011-02-16 10:43 AM
"Today" and "Tomorrow" scripts dbyler OmniFocus Extras 8 2010-06-15 10:21 AM
How to create task with "due date" BUT without "due time" ? fire00 OmniFocus 1 for Mac 3 2010-04-13 11:36 PM
Ability to show time in "in three weeks, in two weeks, tomorrow" formats mr_projects OmniPlan General 1 2007-11-02 11:28 AM
"tomorrow morning"? markbrown00 OmniFocus 1 for Mac 21 2007-06-16 02:19 AM


All times are GMT -8. The time now is 09:39 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.