Let's say I've got 3 workers:
Worker A: PHP coder, Database guy
Worker B: PHP coder, JavaScript
Worker C: HTML/CSS, JavaScript
I'd like to assign tasks to "pools" of talent:
{PHP Coding}, {DB}, {JavaScript} and {Markup}
Is there a method for assigning Worker B to both {PHP Coding} and {JavaScript} so that OmniPlan knows that he's just one resource and honor his work schedule?
If not, what's the strategy to do this sort of thing. I actually have a lot more than 3 workers... :)
Worker A: PHP coder, Database guy
Worker B: PHP coder, JavaScript
Worker C: HTML/CSS, JavaScript
I'd like to assign tasks to "pools" of talent:
{PHP Coding}, {DB}, {JavaScript} and {Markup}
Is there a method for assigning Worker B to both {PHP Coding} and {JavaScript} so that OmniPlan knows that he's just one resource and honor his work schedule?
If not, what's the strategy to do this sort of thing. I actually have a lot more than 3 workers... :)