The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan for iPad
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Separating task effort from duration Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Perhaps I do not understand the distinction between effort and duration.

I have a task that lasts, say, 1 hour, but the assignee can take up to a week to complete the task.

1) Is this the correct way to distinguish effort (the 1 hour) from duration (the week)?

2) In OmniPlan for iPad, can effort and duration be disconnected? (They are locked to equal values now.). How can you disconnect them?

Many thanks!
Doc
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Different units for duration and effort? LJRolf OmniPlan General 3 2011-02-07 11:39 AM
Effort vs. duration vs. period of a task vs. workload Woje OmniPlan General 2 2008-03-20 09:38 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 05:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 12:05 PM


All times are GMT -8. The time now is 11:26 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.