I'm building an HTML template to output project-status information for a client. And we want to show not only the overall / total-project status info (i.e. Completion or % Done) in the HTML version of the report -- but we also want to show the status of sub-sections (grouped tasks) within the project.
However, we can't seem to find info on how to pull the values for specific tasks / grouped tasks within a project -- only the whole-project info.
Has anyone successfully pulled specific task status info using Omni tokens or other means in the HTML export process?
Thanks!
I'm building an HTML template to output project-status information for a client. And we want to show not only the overall / total-project status info (i.e. Completion or % Done) in the HTML version of the report -- but we also want to show the status of sub-sections (grouped tasks) within the project.
However, we can't seem to find info on how to pull the values for specific tasks / grouped tasks within a project -- only the whole-project info.
Has anyone successfully pulled specific task status info using Omni tokens or other means in the HTML export process?
Thanks!