Forum: OmniPlan General 2010-10-22, 03:56 PM
Replies: 12
Views: 6,508
Posted By soitnly
Solved it

There was a disconnect between the work week and the number of hours per day in the project formatting panel. My work week was M-F from 8 to 5 (i.e. 9 hours per calendar day). My project formatting...
Forum: OmniPlan General 2010-10-22, 12:41 PM
Replies: 12
Views: 6,508
Posted By soitnly
It's a bug, I think

Attached are before and after screen shots of a task in the plan I posted last night.

OPlan_01_5days: Note task 2.3.1. Its effort is 5d according to the chart on the left and that matches with...
Forum: OmniPlan General 2010-10-21, 09:39 PM
Replies: 12
Views: 6,508
Posted By soitnly
Trying again...

Hmm... Went through the whole manage attachment process, selecting from the computer, etc. Let me try again...

Ah, there's the problem. The "Upload" button is a separate action from the "Close...
Forum: OmniPlan General 2010-10-21, 08:50 PM
Replies: 12
Views: 6,508
Posted By soitnly
Zipped and delivered!

Thanks for the trick! Yeah, don't want to configure Mail on my work Mac. I've had some Exchange weirdness and don't want to get into issues of whether something is or is not on the server blah blah...
Forum: OmniPlan General 2010-10-21, 07:21 PM
Replies: 12
Views: 6,508
Posted By soitnly
No email formatted

I didn't get any formatted email from which to drag/save an attachment. I'm assuming OP uses Mail, but I haven't configured it. Using Outlook. Any other way to generate a gibberish-y doc?

Thx.
Forum: OmniPlan General 2010-10-21, 12:20 PM
Replies: 12
Views: 6,508
Posted By soitnly
Help with Send Feedback

I can't find the anonymized file on my system. The Feedback dialog says it's going to have a name consisting of part of my email address and date. Can't find it w/ Searchlight. Any thoughts?
Forum: OmniPlan General 2010-10-21, 10:57 AM
Replies: 12
Views: 6,508
Posted By soitnly
Same problem here

I'm also seeing efforts displayed as fractions of days. My tasks start on day one at 8 am and end on day X at 5 (which is what my work calendar considers an entire day: 8-5). However, I end up with...