I've been trying various things, so far with no luck.
I'd like to set an action that is currently sequential to another to have a due date relative to the time it becomes available.
In other words, assuming I have a sequential project with actions:
I'd like "Second action" to have a due date 3 days after I complete "First action". One place this commonly comes up is if I have a Waiting action. "Once I get the email from Bob about what he wants in the TPS report, I need to file my TPS report within 3 days."
I've tried +3d and such under "due", but that just makes dates relative to the current date. Any ideas, or is this a feature request?
I'd like to set an action that is currently sequential to another to have a due date relative to the time it becomes available.
In other words, assuming I have a sequential project with actions:
- First action
- Second action
I'd like "Second action" to have a due date 3 days after I complete "First action". One place this commonly comes up is if I have a Waiting action. "Once I get the email from Bob about what he wants in the TPS report, I need to file my TPS report within 3 days."
I've tried +3d and such under "due", but that just makes dates relative to the current date. Any ideas, or is this a feature request?