Quote:
Originally Posted by akwong View Post
The group duration/effort is the sum of the duration/effort of all the tasks within the group.

To clarify, the feature you want is the ability to create a group, set the group duration to 8 hours, and have the tasks within the group automatically divide up the 8 hours among themselves. Is that correct?
This is correct!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
can I get a violation instead of flowing some tasks in a group to the next block of available time cconstantine OmniPlan General 2 2012-10-18 07:37 AM
Pulling status info for individual tasks when outputting via HTML export m_arts OmniPlan General 1 2010-02-05 04:33 PM
Assign a time window for contexts Pixín OmniFocus 1 for Mac 2 2010-02-04 10:44 PM
Assign a period of time to work on a task each day Ben Greenfield OmniPlan General 6 2007-02-10 06:04 AM
Total Cost blank if assign task to resource group. gregc OmniPlan General 2 2007-02-06 11:15 AM